Challenge
Original design engineer had departed and only a test requirements checklist remained; A universal test system compatible with multiple control boards was needed urgently
Delivered a universal test system compatible with multiple control boards for an in-vitro diagnostics client under incomplete documentation conditions
Original design engineer had departed and only a test requirements checklist remained; A universal test system compatible with multiple control boards was needed urgently
Analyzed interface behavior and rebuilt the test logic, independently completed hardware design (power system, command simulation, signal acquisition), iterated firmware through multiple versions, and developed PC software in parallel
Delivered in under three months; one test system supports multiple control boards; Client continues to choose Ledge for new projects
Delivered a universal test system compatible with multiple control boards for an in-vitro diagnostics client under incomplete documentation conditions
The customer needed a universal test system for multiple control boards, but the original project engineer had left and only a test requirements checklist was available; The goal was to restore test capability quickly enough to support production and validation
Incomplete documentation meant the project could not be developed by simply following an existing design package; Ledge had to analyze interface behavior from the test goals, rebuild test logic, and preserve compatibility across several boards
Ledge started from the test requirements and interface behavior, decomposed test actions and signal paths, then developed test hardware, firmware, and PC software together; Multiple firmware iterations turned uncertain interface behavior into a stable test routine
Ledge delivered in under three months, and one test system now supports multiple control boards; The project restored a practical production and validation capability, not just a one-off fixture